KCT participates in "NordBalt" project

2015 02 12

On February 11 the last power transformer for the „NordBalt“ project was discharged at KCT container terminal.

It was the third shipment of equipment for the „NordBalt“ power link between Sweden and Lithuania.

The first ship was discharged in ro-ro and general cargo terminal with the help of a floating crane last December.

After KCT had acquired a second mobile crane LIEBHERR (124 t), the two following consignments of extra heavy equipment were successfully discharged in container terminal with own cranes.

Twin-lifting of a 196 ton transformer from the ship and positioning it on a special trailer was a challenging operation even for very experienced KCT staff.

More